Redmond Ridge (OneLab)

Description:

Over 57,000 square feet (including generator buildings, switch yard and mezzanine). The building’s cooling method uses outside air with evaporative coolers. Number of Pods: 48 Pods (8 Clusters of 6 pods) separated into two groups of 24 on either side of a central control/work area. UMC designed, built, and commissioned the innovative mechanical systems for this project. Further, the project was a model for prefabrication. Overhead rough-in started March 1, 2009, and the project was fully-commissioned by June 15, 2009.